Main St, Swadlincote: new build covered by a 10 year structural warranty

New build ยท 10 Year Structural Warranty

Main St, Swadlincote

Two two-storey, three-bedroom detached houses on Main Street in Swadlincote, completed in November 2016.

  • 2 homesScheme
  • 5Build stages logged
  • 2016Completed

Inspection record

The build, stage by stage

Each stage was seen before it was covered up. This is the record the warranty is built on.

  1. Stage 1

    Groundworks

    Construction began with groundworks across the plot.

    Main St, Swadlincote: groundworks stage inspection
  2. Stage 2

    Walls

    Brick and blockwork went up under scaffold.

    Main St, Swadlincote: walls stage inspection
  3. Stage 3

    First fix

    Internal studwork went in ahead of plastering.

    Main St, Swadlincote: first fix stage inspection
  4. Stage 4

    Finishes

    Kitchens and internal finishes were fitted.

    Main St, Swadlincote: finishes stage inspection
  5. Stage 5

    Complete

    Both houses were completed at the end of the 52-week contract.

    Main St, Swadlincote: complete stage inspection
  6. Signed off

    Warranty certificate

    With the inspections done and the completion evidence in, the 10 year structural warranty certificate could be issued.

On site

More photos from Swadlincote

Need a 10 Year Structural Warranty (PCC)?

Send your drawings and project details. We'll review what's needed and come back with a clear, fixed quote.

Call us Get a free quote