Nine new homes on the site of the former Jolly Colliers in Newhall, Swadlincote: six semis and three detached houses.

  • 9 homesScheme
  • 15Inspection visits recorded
  • 5Build stages logged
  • 2023Completed

Inspection record

The build, stage by stage

Each stage was seen before it was covered up. This is the record the warranty is built on.

  1. Stage 1

    Foundations

    Foundations were excavated into medium shrinkable clay after ground grouting was finished.

    Former Jolly Colliers, Swadlincote: foundations stage inspection
  2. Stage 2

    Floors

    The ground floor membrane was laid, with joints sealed to the designer's details.

    Former Jolly Colliers, Swadlincote: floors stage inspection
  3. Stage 3

    Walls

    Walls rose past first floor level with joists built in and chipboard decking fixed.

    Former Jolly Colliers, Swadlincote: walls stage inspection
  4. Stage 4

    Roof

    Trusses went up with clips fixed, wall plates bedded and a ventilated dry ridge system.

    Former Jolly Colliers, Swadlincote: roof stage inspection
  5. Stage 5

    Complete

    All internal and external works were finished, with kitchens, bathrooms and tiling in place.

    Former Jolly Colliers, Swadlincote: complete stage inspection
  6. Signed off

    Warranty certificate

    With the inspections done and the completion evidence in, the 10 year structural warranty certificate could be issued.