A six-storey block of 33 apartments replacing an office building on High Street, Harrow.

  • 33 homesScheme
  • 12Inspection visits recorded
  • 5Build stages logged
  • 2026Year
  • Inspections ongoingStatus

Inspection record

The build, stage by stage

Each stage was seen before it was covered up. This is the record the warranty is built on.

  1. Stage 1

    Foundations

    Steel reinforcement went in to the structural engineer's design, with Block A around 90% done.

    High Street, Harrow: foundations stage inspection
  2. Stage 2

    Walls

    Concrete was poured to the columns and reinforcement went in to further columns and the lift, with minimum 40mm cover maintained.

    High Street, Harrow: walls stage inspection
  3. Stage 3

    Floors

    Reinforcement to the first floor was installed to the structural engineer's design and walked on site.

    High Street, Harrow: floors stage inspection
  4. Stage 4

    Floors

    The floor 6 reinforcement was installed to the structural engineer's design, with the engineer's inspection.

    High Street, Harrow: floors stage inspection
  5. Stage 5

    Walls

    The external steel framing system went in, with 15mm fire board to the external face and fire-rated insulation in the frame.

    High Street, Harrow: walls stage inspection
  6. Next

    Final review and certificate

    Once the remaining stages and the completion evidence are in, the 10 year structural warranty certificate can be issued.

Case study

What made this one interesting

The challenge

The job meant taking down an existing office building on the High Street and putting six storeys and 33 apartments in its place. The ground was stripped to evaluate the formation level, and the lower half of the site was reduced before foul drainage and the sub base went in.

How it was handled

We agreed the warranty stages at a site meeting in December 2024 and have inspected against them on 12 visits so far. Each visit walked the reinforcement with the site team, from the base through the columns and lift to each floor in turn. Steel was checked against the structural engineer's design, with minimum concrete cover checked as the floors went up.

The result

The job is still in progress. By October 2026 the reinforcement had reached floor 6 and the external steel framing, fire board and insulation were going on.

On site

More photos from Harrow

Need a 10 Year Structural Warranty (PCC)?

Send your drawings and project details. We'll review what's needed and come back with a clear, fixed quote.