Station Road, Bagworth: new build covered by a 10 year structural warranty

New build ยท 10 Year Structural Warranty

Station Road, Bagworth

Nine detached homes, six bungalows and three houses, built on land next to Station Road in Bagworth.

  • 9 homesScheme
  • 22Inspection visits recorded
  • 6Build stages logged
  • 2024Completed

Inspection record

The build, stage by stage

Each stage was seen before it was covered up. This is the record the warranty is built on.

  1. Stage 1

    Foundations

    Foundations were dug to the structural engineer's design, 1.5m to 2.1m below finished floor level, with two layers of B385 mesh.

    Station Road, Bagworth: foundations stage inspection
  2. Stage 2

    Floors

    Block and beam floors went in to the manufacturer's design with a damp-proof course under the beams.

    Station Road, Bagworth: floors stage inspection
  3. Stage 3

    Walls

    Brickwork and blockwork went up in lifts across the plots.

    Station Road, Bagworth: walls stage inspection
  4. Stage 4

    Roof

    Roof trusses were erected to the manufacturer's design with wall plate straps fixed.

    Station Road, Bagworth: roof stage inspection
  5. Stage 5

    First fix

    Roof tiling was complete with a mechanically fixed ventilated ridge and first fix was starting.

    Station Road, Bagworth: first fix stage inspection
  6. Stage 6

    Complete

    Drain tests were witnessed and all internal and external works were complete.

    Station Road, Bagworth: complete stage inspection
  7. Signed off

    Warranty certificate

    With the inspections done and the completion evidence in, the 10 year structural warranty certificate could be issued.

Case study

What made this one interesting

The challenge

Foundation depths varied across the site, from around 1.0m on some plots to 2.1m below finished floor level on others, all to the structural engineer's design. January 2023 brought waterlogged ground that limited access and slowed the block and beam floors. The site also mixed three home types, with bungalows and houses going up together.

How it was handled

We coordinated Building Control, the warranty and the full set of testing and energy work, with 22 inspection visits through the build. Foundations, floors, brickwork, roofs and first fix were each looked at on site. When the ground was too wet to walk, progress was still recorded with photos from a distance.

The result

By September 2024 all internal and external works were complete, with drain tests witnessed. Fire doors and smoke detectors were fitted and working, and roof tiling was finished with a mechanically fixed ventilated ridge.