Seeds Lane, Brownhills: new build covered by a 10 year structural warranty

New build ยท 10 Year Structural Warranty

Seeds Lane, Brownhills

Five three-bedroom detached bungalows built on Seeds Lane, Brownhills.

  • 5 homesScheme
  • 19Inspection visits recorded
  • 6Build stages logged
  • 2023Completed

Inspection record

The build, stage by stage

Each stage was seen before it was covered up. This is the record the warranty is built on.

  1. Stage 1

    Foundations

    Foundations were dug to the structural engineer's design, 0.6m wide and 1.0m to 1.3m deep in sand and gravel.

    Seeds Lane, Brownhills: foundations stage inspection
  2. Stage 2

    Floors

    Block and beam floors went in with air bricks in position and a damp-proof course under the precast beams.

    Seeds Lane, Brownhills: floors stage inspection
  3. Stage 3

    Walls

    Superstructure blockwork and brickwork went up from the finished floors.

    Seeds Lane, Brownhills: walls stage inspection
  4. Stage 4

    Roof

    Roof trusses were erected to the manufacturer's design, with wind bracing completed and girder trusses fully fixed.

    Seeds Lane, Brownhills: roof stage inspection
  5. Stage 5

    First fix

    First fix plumbing and electrics were completed and the internal timber stud partitions went in.

    Seeds Lane, Brownhills: first fix stage inspection
  6. Stage 6

    Complete

    The drain test was witnessed and all external and internal works were complete.

    Seeds Lane, Brownhills: complete stage inspection
  7. Signed off

    Warranty certificate

    With the inspections done and the completion evidence in, the 10 year structural warranty certificate could be issued.

Case study

What made this one interesting

The challenge

Five detached bungalows went up on sand and gravel with small clay pockets, with foundations 1.0m to 1.3m deep to the structural engineer's design. The plots ran at different stages, with foundations still going in during May 2023 while roof trusses were up on others.

How it was handled

We carried out 19 inspection visits through the build. Each key stage was looked at on site: foundations before concrete, block and beam floors, roof trusses, first fix and drainage.

The result

At the visit on 31 October 2023 the drain test was witnessed and all external and internal works were complete. Guttering and downpipes were connected and clipped, and fire doors with overhead closers were fitted to the integral garages.

On site

More photos from Brownhills